Project Description
The project will replace approximately 780 linear feet of 12-inch wastewater force main and approximately 1,841 linear feet of 20-inch wastewater force main that runs along Quesada Boulevard from the Master Lift Station to the Lion Heart waterway.
Project Location
Quesada Boulevard from the Master Lift Station to the Lion Heart waterway.Project Impacts
Acquisition of pipe and other materials has delayed a portion of the project and has increased the overall project cost.Latest Updates
Installation of the 12" and 20' force main is complete. The contractor is currently working on removing the old force main and restoration of the project area.Budget
Phase | Cost |
---|---|
Construction | $594,803.48 |
Total Budget | $594,803.48 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Design Development | 07/14/2020 | 02/16/2021 | 02/01/2021 |
Construction | 07/05/2021 | 07/29/2022 | 07/19/2022 |
Project Phase
Project Complete
Last Updated
07/19/2022
Project Manager
Hendrik Dolleman
Public Relations
Caroline Wannall
Email Public Relations
Sponsor Department
Utilities
Construction Contractor
Stevens and Layton Inc.